August 27, 2010

Court reviews directed verdict order in a case about a leaky building

E & J CONSTRUCTION COMPANY v. LIBERTY BUILDING SYSTEMS, INC. (Tenn. Ct. App. August 27, 2010)

E & J Construction Company ("Plaintiff") purchased a metal building from Liberty Building Systems, Inc. ("Defendant"). The metal building was purchased by Plaintiff for one of its customers, Camel Manufacturing Company ("Camel"). Plaintiff constructed the metal building for Camel and connected it to an existing building. Almost from the outset, there was a problem with leaking. Plaintiff sued Defendant raising various claims including, among others, breach of contract. After the Trial Court granted Defendant's motion for partial summary judgment, the case proceeded to trial on the few remaining claims. At the conclusion of Plaintiff's proof, the Trial Court granted Defendant's motion for directed verdict. Plaintiff appeals. We reverse the grant of a directed verdict on Plaintiff's breach of contract claim and remand for further proceedings. The judgment of the Trial Court otherwise is affirmed.

Opinion available at:
http://www.tba2.org/tba_files/TCA/2010/ejconstruction_082710.pdf

August 16, 2010

Court reviews breach of contract and prompt pay notice issues in a case involving residential subdivision developers

CLAIBORNE HAULING, LLC v. WISTERIA PARK, LLC (Tenn. Ct. App. August 16, 2010)

Claiborne Hauling, LLC, contracted with Wisteria Park, LLC, to perform the excavating and grading, including installation of storm sewers and sanitary sewers, for a residential subdivision Wisteria was developing. The contract calls for Claiborne Hauling to commence work on November 6, 2006, with a substantial completion date of April 5, 2007. The contract further provides that Claiborne Hauling will receive a bonus of $500 per day for early completion but will pay a $500 per day "penalty" if completion extends past May 31, 2007. Claiborne did not finish by May 31, 2007.

Wisteria "fired" Claiborne Hauling during a heated exchange in August 2007, and confirmed termination of the contract in a letter from counsel. The ground stated for termination is failure to complete the project by May 31, 2007. However, Wisteria did not secure approval of its plans for construction of the sewer system until June 8, 2007.

When Wisteria did not pay the invoices and change orders outstanding at the time of the termination, Claiborne Hauling first sent a "prompt pay notice" and then filed this action alleging breach of contract against Wisteria. Wisteria answered and filed a counterclaim asserting, among other things, that it was entitled to recover $500 per day from May 31, 2007, until substantial completion, as liquidated damages.

After a bench trial, the court found that Wisteria was guilty of the first material breach and awarded Claiborne Hauling a judgment in the amount of $301,430.62, which included attorney fees under the Prompt Pay Act, Tenn. Code Ann. section 66-34-602 (2004). Wisteria appeals. We affirm.

Opinion may be found at:
http://www.tba2.org/tba_files/TCA/2010/claibornehauling_081610.pdf

August 06, 2010

Court reviews suit against Planning Commission challenging their approval of a Planned Unit Development

ANDREW BERNARD SHUTE, JR., ET AL. v. METROPOLITAN GOVERNMENT OF NASHVILLE, DAVIDSON COUNTY, TENNESSEE, ET AL. (Tenn. Ct. App. August 6, 2010)

The Nashville Metropolitan Council approved a Planned Unit Development (PUD) for a large residential subdivision to be constructed by Habitat for Humanity. The Metropolitan Planning Commission subsequently approved a site plan for the first phase of the subdivision, over the objections of neighboring landowners, who then challenged the approval by filing a petition for writ certiorari in the Chancery Court. The petitioners also mounted a challenge against the entire project based on the ground that the PUD had become "inactive" because construction had not yet begun, even though six years had passed since it was initially approved. The Planning Commission rejected the challenge, finding that the project was still "active" and, therefore, that the PUD did not have to go through the process of approval for a second time. The neighbors then filed a second petition for writ of certiorari.

The trial court consolidated the two petitions and heard arguments that the procedures the Planning Commission followed in reaching its decisions violated the petitioners' constitutional rights. The court dismissed both petitions, ruling that the Planning Commission had not acted illegally, arbitrarily or fraudulently, and that the petitioners' constitutional rights were not violated. We affirm.

Opinion may be found at:
http://www.tba2.org/tba_files/TCA/2010/shutea_080610.pdf